How To Fire A Hostile Factory

Wavy lines

The Hostage Situation

The most terrifying sound in the world is not a scream. It is the sound of a heavy iron gate sliding shut behind you in a factory courtyard in Dongguan.

It was 2011. I was young and arrogant. I had flown in to fire a supplier who was making critical hydraulic pumps for my German client. I walked into the General Manager’s office. I put the termination notice on the table. I demanded our molds back.

He smiled. He picked up his phone. He said two words in a local dialect.

Outside, the security guards locked the gate.

“Mr. Victor,” he said, lighting a cigarette. “We have a dispute about unpaid raw material costs. I think your molds will stay here until we settle it. The price is $50,000. Cash.”

I paid. I had no choice. My client’s production line in Munich was waiting.

That day, I learned a lesson that no MBA program teaches: Possession is 100% of the law.

If a supplier has your tooling (molds) and your inventory, they own you. If you try to fire them like you fire an employee, you will lose.

Firing a supplier is not an administrative act. It is a special operations mission. It requires deception, camouflage, and speed.

Here is the “Victor S. Protocol” for the Silent Extraction.

Phase 1: The “Honeymoon” Camouflage (The Lie)

Most procurement managers signal their intent too early. They get angry about quality. They stop answering calls. They start arguing about invoices.

This is a rookie mistake. When you are planning to fire a supplier, you must become their best friend.

You need to buy time. You need to sedate them.

The Tactic: Three months before the breakup, I launch a “Partnership Program.” I visit the factory. I take the owner to a miserable, expensive dinner. I toast to our “Long Term Future.”

I tell them: “We are planning a massive expansion next year. Volumes will double. We need you to be ready.”

This is a lie. But it is a functional lie. It makes them greedy. It makes them relax. They think, “I am safe. I am the golden child.”

While they are dreaming of the new volume, I am quietly preparing the knife.

Phase 2: The Oxygen Tank (Building the Secret Buffer)

You cannot fight if you cannot breathe. In the supply chain, inventory is oxygen.

If you fire the supplier today, production stops tomorrow. You need a bridge to get you to the new supplier.

The Tactic: I start increasing my orders. But I do it subtly. I do not place one giant order (that looks suspicious). I increase the weekly order by 15%. “Sales are slightly up,” I tell them. “Just a seasonal spike.”

I divert this extra stock to a Secret Warehouse. Do not send it to your main warehouse if the supplier has access to your inventory data (VMI). Rent a third-party logistics (3PL) shed.

I keep building this buffer until I have 3 months of stock sitting in safety. This is my leverage. If the supplier stops shipping the day I fire them, I can survive for 90 days. That is enough time to spin up a new source.

Phase 3: The “Trojan Horse” Audit (Stealing Your Own IP)

Do you actually own your product? You think you do. You have the PDF drawings.

But the factory has the real data. They have the “CAM Files” (Computer-Aided Manufacturing) that tell the CNC machine how to cut the steel. They have the “Process Recipe” (temperatures, pressures, cycle times). They have the list of sub-suppliers who make the springs and the O-rings.

If you leave without this data, your new supplier will take six months to relearn it.

The Tactic: I send in a “Process Engineer” to the factory. I tell the owner: “Since we are going to double the volume next year (the lie), I need my engineer to help you optimize the cycle time. He is here to help you save money.”

The owner welcomes him. “Free consulting! Great!”

My engineer is not there to help. He is a spy. He stands by the machine. He writes down the settings. He takes photos of the sub-supplier labels on the raw material boxes. He copies the injection parameters.

He is building the “shadow dossier.” When we walk out, we have the recipe. We don’t need the chef anymore.

Phase 4: The “Overflow” Decoy (Setting up the New Wife)

You cannot move the molds until the new supplier is ready. But how do you test the new supplier without the molds?

You use the “Overflow” excuse.

I go to the new supplier (Supplier B). I tell them: “I have a main supplier. But they are full. I need a second source for the overflow volume.”

I pay Supplier B to build Duplicate Tooling for the critical parts. Yes, this costs money. Maybe $50,000. Do not be cheap. This is the cost of freedom.

I validate Supplier B using the new tools. I make sure their quality matches the old supplier. Now, I have two operational factories.

  • Supplier A (The Target): Still running at 100% capacity.
  • Supplier B (The Assassin): Ready and waiting.

Phase 5: The “Upgrade” Extraction (Getting the Molds)

This is the most dangerous moment. The “Switch.”

You have the inventory buffer. You have the recipe. You have the new supplier ready. Now you need to get your assets (the heavy steel molds) out of Supplier A’s factory.

If you say: “I am firing you, give me the molds,” they will lock the gate. You must lie one last time.

The “Maintenance” Ruse: I tell the owner: “We have a small engineering change. We need to modify the logo on the mold. It will take 2 days.” “My truck is coming to pick up the mold to take it to the specialized tool shop for the modification.”

The owner believes me. Why wouldn’t he? We are “partners.” We are planning a “volume increase.”

He loads the mold onto my truck. The truck drives out of the gate. The driver does not go to the tool shop. He drives straight to Supplier B.

Once the mold is inside Supplier B’s factory, I breathe. The bomb is defused.

Phase 6: The “It’s Not You, It’s Me” Email

Only when the truck is safe, and the inventory is secure, do I drop the mask.

I do not call. I do not visit. It is too emotional. I send a formal letter.

“Dear [Owner Name], Due to a strategic realignment of our global manufacturing footprint, we are consolidating our supply base. Effective immediately, we are ceasing orders. All outstanding invoices will be paid according to the contract. We wish you the best.”

It is cold. It is corporate. It is final.

The owner will call. He will scream. He will threaten to sue. Let him. You have the molds. You have the stock. You have the data. He has nothing.

Phase 7: The “Cleanup” (Dealing with the Fallout)

There will be noise. He might try to sell your leftover parts on the grey market. He might badmouth you to other suppliers.

The “Zombie” Order: To keep him quiet for the first few weeks, I sometimes leave a small “zombie” order on the books. I tell him: “We are stopping the main line, but we still need spare parts. Keep the line open for spares.”

It gives him a glimmer of hope. It stops him from doing something desperate. Then, six months later, I cancel the spares too.

Final Thoughts: The Price of Independence

You might think this is cruel. “Victor, where is the honor? Where is the trust?”

I will tell you where the trust went. Trust died the moment that supplier decided to hide a quality failure. Trust died when they raised the price three times in one year without justification.

In the supply chain, you are a guardian of your company’s survival. If a supplier becomes a cancer, you must cut it out. You cannot ask the cancer to leave politely. You must operate.

The goal is not to be liked. The goal is to keep the production line moving.

Be nice. Be prepared. And keep the gate open.